Stellantis has until about Dec. 12 to answer a formal notice of default from Canada's federal government over Brampton Assembly, the idled Ontario car plant it has agreed to sell to armored-vehicle maker Roshel. The two sides are far apart on money. Ottawa says the automaker owes hundreds of millions of dollars; Stellantis has offered to hand back C$24 million.
The next test comes Friday, Nov. 20. Industry Minister Mélanie Joly is due to meet Stellantis CEO Antonio Filosa in Toronto, alongside Ontario officials and the Unifor union, her office told CTV News. All figures below are in Canadian dollars unless noted.
What the notice says
Joly sent the notice on Nov. 12 in a letter to Stellantis Canada CEO Trevor Longley. The government hasn't published the letter or issued a release; its contents are known through reporting by The Canadian Press.
According to that reporting, the letter lists four breaches of a 2022 funding agreement: halting the Jeep Compass program at Brampton, failing or refusing to name a replacement vehicle, keeping no production at the site, and closing it. Stellantis has 30 days to show it will fix them. If it doesn't, Joly says she will declare the company in default, which could end the agreement and trigger a demand for all or part of the money, plus interest. The letter also leaves room to add breaches tied to the Roshel sale.

Under the 2022 deal, Ottawa committed up to $529 million toward retooling Brampton and Windsor Assembly, the Ontario plant that builds the gas and electric Dodge Charger. The government hasn't said how much it actually paid. Federal records cited by CTV News and CBC show $222 million had gone out by March 2025, a total that covers both plants.
Two numbers, two positions
Ottawa. “Stellantis is on the hook for hundreds of millions of dollars,” Joly said, as quoted by Global News. After a 90-minute meeting with the company, Unifor, and Ontario on Nov. 12, she told reporters she was fed up and that Ottawa would sue if nothing changes inside the 30 days. A day later she said the company “cannot close the plant.” CP24 reported that she also acknowledged Ottawa can't block the sale itself under the Investment Canada Act, because the seller is Stellantis' Canadian subsidiary, and that she pointed to the funding agreements as the government's leverage. Joly says Ottawa and Ontario have put what she calls an aggressive package in front of the company to prevent the sale.
Stellantis. Longley said the company “will voluntarily return” the $24 million in federal support it received for Brampton's original retooling plan. Stellantis says the Roshel deal puts the site back into industrial use, and that confidentiality provisions keep it from giving more detail on the funding.
Ontario. The province committed $513 million to the same project, including $132 million for Brampton, Global News reported. Economic Development Minister Vic Fedeli says Ontario has advanced about $55 million, all of it for Windsor and none for Brampton. A separate 2023 federal-provincial incentive worth up to $1.5 billion over 10 years, for Stellantis' Windsor battery plant, requires the company to keep its Ontario footprint through 2035, Brampton included, according to the same report.
Unifor. National President Lana Payne said the Nov. 12 meeting ended with no commitment from either government to undo the deal, and that reversing a signed sale would be “doubly difficult.” The union represents more than 9,000 Stellantis workers in Canada. More than 2,000 of them have been on layoff at Brampton since the plant stopped building cars in December 2023.

How a Jeep decision became a contract fight
Brampton built the Dodge Charger, Dodge Challenger, and Chrysler 300 until December 2023, then shut down to be retooled for the next Jeep Compass. Stellantis paused that work in February 2025, after the U.S. imposed a 25% tariff on Canadian-built vehicles. In October 2025 it assigned the Compass to Belvidere Assembly in Illinois as part of a US$13 billion American investment plan.
Joly opened a dispute-resolution process that month and told a parliamentary committee on Dec. 4, 2025, that a first notice of default had been served. The Roshel agreement, announced Nov. 9, is what ended that process. The tariffs behind the original decision remain in place, and who in Washington can change them is a separate question.
What's next: Friday's meeting with Filosa, then the end of the 30-day window around Dec. 12. The Roshel sale is expected to close by the end of 2026, and neither company has disclosed the price. Stellantis says it employs more than 10,000 people in Canada outside Brampton.